| Project # | 1826 |
| Account Name | The Cove |
| Developer | THE LAGOONS PHASE ONE L.L.C |
| Registration Date | 07/11/2016 |
| Completion Date | 14/12/2020 |
| Escrow # | 019000029849 |
| Bank Details | MASHREQ BANK PSC |
| Milestones | Percentage (%) |
| 1st Installment | 12% |
| 2nd Installment | 8% |
| 100% Construction and Handover | 0% |
| 3 months after completion | 10% |
| 6 months after completion | 10% |
| 9 months after completion | 10% |
| 12 months after completion | 10% |
| 16 months after completion | 5% |
| 20 months after completion | 10% |
| 24 months after completion | 5% |
| 28 months after completion | 10% |
| 32 months after completion | 5% |
| 36 months after completion | 5% |
The developer of this project offers a 2% DLD Waiver when purchasing an apartment in this complex.